The VIA Rail Toronto Maintenance Centre Modernization project will include significant upgrades within the existing rail yard to accommodate 32 new trainsets.
The Toronto Maintenance Centre (TMC) project includes the demolition of a portion of the existing structure of Building C, construction of a new maintenance building addition, removal, and replacement of tracks, as well as the addition of a stand-alone Wheel Lathe Facility, and critical infrastructure improvements throughout the maintenance yard.
- Location
- Toronto, ON
- Completion Status
- 2026
- Client
- VIA Rail Canada
- Key Personnel
- Jim Strasman, Bina Puri, Sim Posen
- Project Types
- Transit
The TMC project scope highlights include:
Partial demolition of the existing main building
Modification to the existing main building
New maintenance building addition
New Wheel Lathe building (to maintain wheels and ensure smooth operation on the tracks)
Infrastructure and Trackside Service Building (TSB) for Vehicle Equipment Measurement Systems (VEMS)
Fueling upgrades
Stabling upgrades
State of Good Repair Work
The new maintenance buildings seek to maintain a similar visual and aesthetic to the existing facilities, while incorporating important changes such as windows that are translucent glass on the south and clear vision glass on the north to allow ample natural light into the interiors and improve the quality of the workspace.




TMC in progress (July 2023) Picture Courtesy of Buttcon Ltd.